Field Engineering


To insure good performance of the inlay, the inlay fi ller metal should be compatible with the bellows material and base metal. The fi nished inlay should receive 100% dye penetrant examination. The inlay can be post weld heat treated if the Chrome Moly base metal is to be heat treated in accordance with the fabrication specifi cation. However, the inlay itself is adequate insurance against leakage through the heat-affected zone. An additional heat treatment specifi cally for the inlay is not considered necessary for reliable bellows attachment weld performance.

  • Avoidance of future problems, unplanned shutdowns and safety hazards
  • Fast track response from SFP in emergencies working from accurate site data
  • Opportunity to purchase spare parts on a nonemergency basis if developing problems are identifi ed which could cause an unplanned shutdown
  • Early identifi cation of work for planned maintenance

SFP provide broadly 4 levels of site inspection and reporting for clients covering all types and manufacturers' expansion joints.
  • Level 1 - Walk through of plant
  • Level 2 - On line inspection
  • Level 3 - Off line inspection
  • Level 4 - Full pipe stress and line condition study

Level 1 - Walk through of plant on-line or off-line
This inspection would be carried out by an experienced engineer from SFP to provide an overall visual assessment of the joints and piping conditions in the plant.

Scope:
  • Visual inspection using existing permanent access routes, walkways and platforms for access
  • No covers removed or physical intervention on the joints
  • Any existing, permanent test points accessible would be checked
  • Position of pipe hangers and overall line conditions noted
  • External condition of joints noted including hardware, obvious signs of leakage and apparent movement of joint

A brief visit note would be issued highlighting any concerns and suggestion further action required.

Level 2 - On line inspection
This inspection would be carried out by an experienced Engineer from SFP to provide a detailed external assessment of the joints and piping conditions in the plant.

We recommend prior to the survey the following is arranged:
  • Good physical access to all expansion joints (scaffolding work, platforms etc)
  • Removal of covers and insulation and/or lagging
  • Applicable drawings for subject expansion joints to be inspected or SFP references prior to visit.
  • General arrangement of piping system drawings, if applicable.
  • Identity and tag each expansion joint per location and type of expansion joint.
  • Visually inspect each expansion joint bellows for the following: leaks, dents, convolution uniformity, discoloration, foreign materials, longitudinal and bellows attachment weld cracking.
  • Visual inspection of all piping components associ ated with an expansion joint, i.e. spring supports, guides and anchors where accessible. All acces sible guides and spring supports will be marked in the hot condition.
  • Pressure test of two ply bellows to confi rm integrity where access allows
  • Dimensionally inspect the bellows with regard to overall length, tie rod nut gaps, slotted hinge gaps, angular rotation (for gimbal and hinged units) and comment on the measured movement versus the design movement of the expansion joint.
  • Temperature reading (whenever applicable) on various locations of the bellows and pipe wall.
  • Inspect hardware welds where accessible.
  • Inspect for general distortion of hardware, missing hardware, etc.
  • Full written report of fi ndings per joint and recommendations for action

Level 3 - Off line Inspection
This inspection extends the Level 2 scope with internal and weld inspections.

We recommend prior to the survey the following is arranged:

  • As per Level 2 plus:
  • Man way accessibility, lighting and ventilation, when applicable.

Scope:
  • As per Level 2 plus:
  • All accessible welds both dye penetrant tested and visually inspected.
  • Sampling and analysis of any foreign material found in expansion joint.
  • Magnetic particle testing, positive material identifi cation utilizing Texas Nuclear Analyser, ultrasonic testing and replicate testing, when applicable.
  • Visually examine all accessible wetted surfaces from inside the expansion joint.
  • Inspect liner cavity, packing, refractory and liners, when applicable
  • Verify design movements versus actual movements when reference is available.
  • Extended written report of fi ndings per joint and recommendations for action

Level 4 - Full pipe stress and line condition study

The inspection and engineering analysis will be undertaken by one of SFP’s fully qualifi ed pipe stress engineers:

Scope:

  • Pipe stress analysis using CAESAR pipe stress analysis programme
  • Finite Element Analysis (FEA) using the COSMOS or ALGOR FEA programme
  • Customer developed engineering programmes for the analysis and design of expansion joints, supports, anchors and guides
  • Training seminars
  • Fully detailed written report and output.

SFP Site Service Solutions are deigned to reduce both cost and operational risk and ensure your maintenance investment delivers best value over many years of successful and trouble free operation.