Three-Day Fabrication of Expansion Joint


Keeps Nuclear Power Plant On-line


On January 9th VEPCO’s North Anna Nuclear Generating Station, Unit 2 was told by the NRC that they had just seven days to replace a failing pump discharge metal bellows expansion joint on their recirculation spray line or shut down the 975-MW unit. The expansion joint’s centerline had moved 3 inches out of alignment with its flanges due to “squirm” failure. The verbal order from VEPCO was received by Senior Flexonics Pathway Bellows on January 10th. The replacement (10 inch diameter by 23 inch long metal bellows expansion joint, rated at 180 psig, 260°F and fabricated from 0.037 inch thick type 304 stainless steel) was manufactured “from scratch” and shipped from Oak Ridge, Tennessee via VEPCO’s private plane at 7:15 PM on the 12th -order-to-shipment was less than 60 hours! According to one VEPCO representative at the North Anna Plant, “I would never have believed that this fast turn around was even possible. On the 9th, we were certain we faced an unscheduled outage in a week. On-site NRC officials were as amazed as I was.” The chronological summary of these three days between order and shipment attests to the cooperation between VEPCO,Senior Flexonics Pathway and Path way’s vendors, and the Senior Flexonics Pathway “can-do-it” spirit.

January 11th
VEPCO’s on-site inspector and Senior Flexonics Pathway engineers review requirements, material procurement, and shipping schedule.

Reynolds Aluminum in Cincinnati breaks into their production schedule, and a truck is dispatched to pick up special plate for the expansion joint lugs. Flanges are ordered from Houston to be shipped via Delta Dash for same day delivery.

This replacement expansion joint did not require Senior Flexonics Pathway to have an ASME nuclear stamp and ASME Section Vlll materials could be used. However, a total of six tests would be required to insure integrity necessary for a nuclear installation.

10:30 AM - Engineering revises drawings to reflect current standards, and the job is released for manufacture.
11:30 AM - Material samples are sent to an independent laboratory for physical and chemical testing.
1:30 PM - Quality Assurance beings a documentation package.
4:00 PM - Fabrication starts with VEPCO’s witness present.
8:00 -11 :30 PM -Vendor materials arrive by truck and plane. Fabrication continues.

January 12th
9:00 AM - Bellows is now complete; final assembly begins.
1:00 PM - Dye-penetrant check completed.
3:15 PM - The test results come back from the independent laboratory, and final documentation proceeds.
4:00 PM - The ASME Code inspector arrives, and hydrostatic testing begins
6:45 PM - The expansion joint is packaged for shipment.
7:15 PM - SHIPPED!

For more information contact: Senior Flexonics Pathway.